Request A Quote

Close
  • Request A Quote
  • Applications

    Municipal Water Tanks

    The modular nature of the system enables quick, cost effective installation in even the most remote locations, on a limited footprint, making the system ideal for municipal and community-based installations. The product is suited to the storage of potable (drinking) water, effluent (waste) and leachate (from processing) and can be installed as part of the water treatment process.

    Engineer designed and approved water storage solutions.

    Applications

    SBS® offers a wide range of water and liquid storage solutions to meet the diverse and exacting needs of the mining, municipal, fire protection and commercial sectors, with a focus on working to develop comprehensive solutions that address the need for water conservation.

    Applications

    SBS Energy has developed a solution that not only addresses the need for backup power, but puts the power back in business owner's hands with an easy-to-use dashboard system.

    Case Studies

    A New Era For Municipal Reservoirs: Steel Water Storage Tanks

    Kirkwood Water Supply Scheme Reservoir Project

    Location: Kirkwood and Bontrug, Eastern Cape, South Africa

    Challenge: The Sundays River Valley Municipality required additional treated water storage to maintain reliable supply to multiple communities during planned canal maintenance shutdowns and improve long-term water security.

    SBS Solution: SBS Tanks supplied and installed two ST31/09 modular steel panel reservoirs with a combined storage capacity of approximately 6 million litres. The project included engineering support, manufacturing, delivery, installation, commissioning and project management in partnership with Ruwacon and Newground Projects.

    Result: The completed reservoirs provide critical backup water storage for Kirkwood, Aqua Park, Bergsig, Moses Mabhida and Msengeni, improving system resilience and ensuring continuity of supply during maintenance periods.

    Case Studies

    Bulk water storage tank for Nelson Mandela Bay Metro

    The Nelson Mandela Bay Metropolitan Municipality has been experiencing water challenges for
    several years. As part of one of nine initiatives implemented by the municipality, which comprises
    Gqeberha and Kariega (previously known as Port Elizabeth and Uitenhage respectively), a 460,000
    litre bulk water storage tank from SBS® Tanks was installed.

    Case Studies

    Fast and effective solution delivered for raw seawater storage

    Anticipated increased water demand from the neighbouring seaside resort towns of Bushman’s River Mouth and Kenton-on-Sea necessitated an increase in the raw seawater storage capacity at the Albany Coast Reverse Osmosis Plant. Situated on the Bushman’s River Mouth the plant abstracts water from wells for desalination for bulk supplier, Amatola Water/Amanzi Board.

    Case Studies

    Karoo Community faces water secure future

    In Jansenville, a bulk water storage tank from the SBS Tanks Standard Tank Range was installed to provide an effective 1.3Ml of water storage capacity. The SBS Tanks engineering team designed a specialised ring beam, which was constructed on the existing concrete floor of the old reservoir. Several other design elements were required to ensure that the water, sourced from various boreholes, moved through to the supply tank free and clear of the naturally occurring sediment.

    Case Studies

    Keeping Education Flowing at the University of Zululand

    SBS is in the process of designing and installing a 5Ml water storage and treatment plant at the University of Zululand- to help the university overcome repeat water cuts due to illegal connections.

    Case Studies

    MUNICIPAL Water Tanks: SBS Tanks Partners with eThekwini Municipality

    A successful installation of a 50kl pump station tank and a 1.7Ml bulk water storage system for our first collaboration with the eThekwini municipality!

    Case Studies

    SBS Tanks blend seamlessly into Karoo landscape

    The Klipplaat community, approximately 30 kilometres from Jansenville in the Dr Beyers Naude Municipality recently became more water secure. As part of a project funded by the Department of Water and Sanitation, SBS Tanks installed an ST21-05 to deliver 775kl of water storage for the area. Due to space limitations, the SBS bulk water storage tank was installed on the floor of the old reservoir after contractors demolished the concrete walls.

    The Jansenville community also benefitted from a water storage tank installation and to help blend the tanks into the natural surroundings, and “match” them to the existing concrete reservoirs which they were installed alongside, the client chose colours from the SBS Tanks powder coated colour range. In Klipplaat the colour Sahara was used, and in Jansenville, the colour Chalk.

    Case Studies

    Tank Farm installed to increase bulk potable water storage

    SBS Tanks installed a quick and cost-effective solution to increase bulk potable water storage for the KwaGuqa township, situated west of eMalahleni. The tanks have a combined storage capacity of over 15 million litres and are modular, steel-bolted water storage tanks offering a fast and effective solution for bulk water storage at a community level.

    Case Studies

    Two new bulk water storage tanks for Zululand District Municipality

    At Makhosini, in Zululand, the tanks, installed by SBS Tanks’ in-house installation teams, hold a combined capacity of 750,000 litres of water storage. The SBS tank model, ST17/06 provides the bulk of that storage capacity at 600,000 litres and stands just over six metres tall, while the ST13/03 accommodates 150,000 litres of water and stands just over three metres high.

    Case Studies

    Superspar Witbank Copy

    Requirements:

    The client required a solution that would produce as much alternate energy from solar to offset costs and integrate with a 1.2MW Generator.

    Solution:

    SBS Energy installed a 500kW peak grid-tied solution flooding all available roof space with solar.

    Case Studies

    Azura Offices

    Requirements:

    Cost saving and back-up energy to ensure that the Azura offices remain operational durning load shedding.

    Solution:

    SBS Energy installed 44kW of PV on tilt racks with a 100kW Atess inverter coupled to a 200kWh Freedom Won battery.

    Case Studies

    Superspar Witbank

    Requirements:

    The client required a solution that would produce as much alternate energy from solar to offset costs and integrate with a 1.2MW Generator.

    Solution:

    SBS Energy installed a 500kW peak grid-tied solution flooding all available roof space with solar.

    Case Studies

    Berea Centre

    Requirements:

    Find cost savings through alternate energy supply.

    Solution:

    SBS Energy installed a 375kW Peak grid tied solar solution.

    Case Studies

    Cabriolet Auto

    Project Requirements:

    Looking for an alternate energy solution to offset day time consumption and realise savings.

    Solution:

    SBS Energy installed a 90kW grid tied solar solution.

    Case Studies

    Gace Farming

    Project Requirements:

    To provide Gace Farming with a cost saving through the production of alternate energy. Gace farming was also faced with the problem of not being able to increase their supply from Eskom. As the farm has expanded over the years, the energy requirement now exceeds that of the current supply so the they needed supplementary supply from solar.

    Solution:

    SBS Energy installed a 120kW peak grid tied solar solution, integrated with a 100kVa generator.

    Case Studies

    TerraMacs Farming

    Requirements:

    Provide savings and power to the TerraMacs farming operation, including the irrigation and fertigation plants, and the homestead.

    Solution:

    SBS Energy installed 22kW of PV coupled to 2 x 12kW Sunsynk inverters, with a 40kWh Freedom Won battery.

    Case Studies

    Ellingham Farm Offices

    Requirements:

    Keep the offices at Ellingham farm running through load shedding.

    Solution:

    SBS Energy installed 22kW of PV coupled to a 2 x 12 Sunsynk inverters, with 20kWh of battery storage.

    Case Studies

    Cole Farming – Dam

    Requirements:

    Cost saving and back-up energy to ensure that the irrigation and fertigation plant for the macadamias remained operational during load shedding and grid failures.

    Solution:

    SBS Energy installed a 22kW PV ground mount array with a 50kW Sunsynk inverter coupled to a 60kWh Freedom Won battery.

    The ground out was designed and installed by the SSB team and is part of the turn key solution offered by SBS Energy. The ability to keep the process in house allows the SBS team greater control on deliverables whilst saving on cost.

    Case Studies

    Cole Farming – Main

    Requirements:

    Cost saving and back-up energy to ensure that all farming operations and the homes on the farm would remain operational durning load shedding.

    Solution:

    SBS Energy installed a 80kW PV ground mount array with a Atess 100kW inverter coupled to a 200kWh Freedom Won battery.

    The ground mount was designed and installed by the SSB team and is part of the turn key solution offered by SBS Energy. The ability to keep the process in house allows the SBS team greater control on deliverables whilst saving on cost.

    Case Studies

    Scribante Farm

    Requirements:

    Hybrid solar solution for the house and stable complex.

    Solution:

    SBS Energy installed a 40kWh Freedom Won battery storage solar solution with 24kW of inverter capacity.

    Case Studies

    Mackenzie Farms

    Requirements:

    Back-up energy solar energy solution to ensure that milking and refrigeration would be maintained despite load-shedding and power interruptions.

    Solution:

    SBS Energy installed 100kW of PV, with 3 x 50kW Atess inverters and 200 KWh of battery storage from Freedom Won.